MULTI-MILLION POUND TESCO INSTALLATION PROVIDES EASILIFT WITH ITS BIGGEST EVER LOAD

MEDIA INFORMATION

REF:        ELS 184                                      DATE:  20 July 2011

EMBARGO:        For Immediate Release

MULTI-MILLION POUND TESCO INSTALLATION PROVIDES EASILIFT WITH ITS BIGGEST EVER LOAD

Easilift Loading Systems has recently completed the largest single order ever placed in the UK for loading bay equipment. The bespoke solution for Tesco's new state-of-the-art Grocery Distribution Centre in Daventry saw Easilift successfully deliver a project worth in excess of £6.5M

The 800,000 sq ft facility is a major investment designed to meet Tesco's long-term distribution requirements. Easilift, already an existing supply partner to Tesco, was recruited to take care of the Grocery Distribution Centre's widespread and complex loading dock requirements.

Working closely with Tesco and the main contractor Volker Fitzpatrick, Easilift project managed the installation of 40 double deck lifting platforms and 100 dock leveller bays, all housed in external loading pods. The high specification of the build together with the complex design issues and tight programme required the attention to detail that Easilift are renowned for.

"Easilift has proven its abilities in the past, and we knew that by involving them in the process from the start, we could maximise resources to deliver a robust loading bay environment on a scale never attempted before in UK distribution," explains Duncan Robertson, Project Manager at Tesco.

The design interface was critical to the success of the project and Easilift worked closely with the project team to overcome a number of technical challenges. Notably, spatial restrictions at yard level meant that the double deck bays had to be constructed in pairs. This innovative arrangement created a tandem pod around a single walkway to ensure safe and easy operator access / egress.

Each of the 40 double deck bays incorporates a heavy duty, surface mounted 16,000kg lifting platform, capable of carrying up to 30 roll cages. The lifts are located within external modular pods, manufactured and partially preassembled at Easilift's Huddersfield factory prior to delivery and final on-site erection using a 60-tonne crane. This approach equated to a 60% reduction in installation time for this particular element, when compared with previous lift installations.

The dock leveller bays comprised 96 Type 232 PoweRamp hinged lip units and 4 Type 233 PoweRamp telescopic lip units, with each bay comprising a modular loading pod, a Type 403 PowerShelter and a 601 PowerDoor.

Ancillary equipment supplied throughout all bays included environmentally friendly LED traffic and loading dock lighting, pod lights, fully integrated control panels and heavy duty "slider" bumpers.

Furthermore, in line with Tesco's commitment to improving site safety all "goods in" bays were fitted with the revolutionary new Dock Management System developed by Easilift and Traka. This innovative hi-tech management reporting and safety system is designed to prevent the premature departure of vehicles from the loading bay.

The system combines Easilift’s dock door and associated control equipment with Traka's electronic key control system and was tailored to complement Tesco's existing safety processes, creating a high-tech solution to the problem of vehicle drive-off accidents.

The success of the project, which went live in May 2011, underlines Easilift's ability to achieve large-scale and technically demanding projects. The bulk of the installation was completed during the winter months of 2010/2011, where Easilift was able to fit equipment on time and within budget despite the extreme bad weather which plagued the UK.

"In terms of size and scope, the development of the Grocery Distribution Centre has been a huge undertaking, and Easilift has met our requirements every step of the way," confirms Duncan Robertson.

ENDS

Notes To Editors

With 35 years’ experience in the design, manufacture, installation and maintenance of high quality loading bay equipment and industrial doors, Easilift Loading Systems is the UK’s leading specialist supplier of total loading bay solutions to some of the biggest names in retailing, manufacturing, logistics, distribution, warehousing, building, construction, and the service sector.

The company provides a complete range of loading bay equipment, including dock management systems, dock levellers, dock shelters & seals, industrial & high speed doors, advanced control centres and lifting platforms, together with a wide selection of accessories and safety aids such as dock plates, dock bumpers, dock & traffic lights, wheel guides & vehicle restraints and integrated control systems.

Easilift was also one of the pioneers in the design and installation of dock pod systems, which are complete stand-alone loading bay enclosures that can be installed directly onto the external face of a building. Suitable for new buildings, extensions and refurbishments, they can be quickly and easily re-positioned, if required, and are ideal for use with the increasingly popular and highly cost-effective double deck trailer units.

As the UK’s leading loading bay specialist, Easilift was one of the first in its sector to achieve the prestigious SAFEcontractor accreditation in recognition of its health and safety record and competency, confirming to prospective customers that effective policies and systems are in place.

Easilift is a member of the Loading Systems International Group, one of Europe’s foremost manufacturers of loading bay equipment. The Group has over 450 employees across Europe and a total turnover in excess of 60 million Euros.

Also an active member of the Association of Loading & Elevating Equipment Manufacturers (ALEM) and the Confederation of Construction Specialists, Easilift operates to the international ISO 9001:2008 quality management standard. The company has Investors in People Bronze status accreditation and is a participant in the Construction Skills Certification Scheme, with all its engineers fully qualified under the CITB Site Supervisor Safety Training Scheme.

For information about their market-leading total loading bay solutions contact: Easilift Loading Systems Ltd, Spring Grove, Penistone Road, Kirkburton, Hudderfield, HD8 OPL. Tel: 08451 301920. Email: sales@loading-systems.co.uk  Web: www.loading-systems.co.uk  

High resolution photos to accompany this release are available by clicking here.

Photo Captions:

(A) Easilift Loading Systems has recently completed the largest single order ever placed in the UK for loading bay equipment.  The bespoke solution for Tesco’s new state-of-the-art Grocery Distribution Centre in Daventry saw Easilift successfully deliver a project worth in excess of £6.5M.

(B) The high specification of the build together with the complex design issues and tight programme required the attention to detail that Easilift are renowned for.

(C) Spatial restrictions at yard level meant that the double deck bays had to be constructed in pairs.  This innovative arrangement created a tandem pod around a single walkway to ensure safe and easy operator access / egress.  

(D) The dock leveller bays comprised 96 Type 232 PoweRamp hinged lip units and 4 Type 233 PoweRamp telescopic lip units with each bay comprising a modular loading pod, a Type 403 PowerShelter and a 601 PowerDoor.

ISSUED BY/MEDIA ENQUIRIES TO:
McConnells Public Relations
49 Uttoxeter New Road
Derby
DE22 3NL
Tel: 01332 222900
Email: simonk@mccgp.co.uk
Web: www.mccgp.co.uk
Contact: Simon Kinnear
PR Account Manager

ISSUED ON BEHALF OF:
Easilift Loading Systems Ltd
Spring Grove
Penistone Road
Kirkburton
Huddersfield
HD8 0PL
Tel: 08451 301920
Fax: 01484 601401
Email: sales@loading-systems.co.uk
Web: www.loading-systems.co.uk
Contact: David Whyatt
Sales Director

Text and image/s © 2011 Easilift Loading Systems Ltd and McConnells Group

McConnells and its client/agents reserve the right to make photocopies/digital copies of any editorial media coverage arising from its press releases and articles, free of any payments to media owners and/or their agents or other bodies.


Issuers of news releases, not Targetwire, are solely responsible for the accuracy of the content.